I supposed it could be %Work Complete and the formula I was thinking about using would be something like:
Early Finish = Todays Date + (1 - %work Complete/100) * Work
... possibly Duration could be used instead of work.
Looking forward to hearing your reply.
Thanks
Cheers,
Dalgetty
Hi,
Is there a way to get MS Project to calculate the Early Finish (or any other finish date) given:
- % complete on tasks
- duration or work
- todays date
say that todays date is X (say 1st Sep). The task's duration is say 10 days. It is 40% complete. I would like to see the Early Finish...