Hi.. thank you for the post, but unfortunately it dosnt help as I am working on a project to migrate over 300 project plans.
unfortunately simply copying and pasting from excel to MSP is not a viable option.
I have already produced a data map in MSP. I have found that if a task has an entry...
Hi All...
I have the following problem importing poject data from excelinto MSP.
I am importing "start","finish", "duration"(finish-start
+1), "actual start" date and "actual finish" date.
The problem is that the finish date seems to be defaulting to yesterdays date as opposed to the date...