Actually, it's one business day. If the date in Excel is a Monday, the finish date in Project will be the Friday before. We're really not using Project as it is intended. The employee I replaced had a schedule set up that is basically using our contract as the project and work orders as tasks...
Whenever I import data from Excel into Project, the Finish date is always one day earlier than the date in the Excel spreadsheet. Does anyone know why this is and how to correct it?