Ok, not what I would have liked to hear, but at least the confirmation from a pro, that I am not missing a key feature here.
The MS Project leveling algorithm is just not clever enough...
Thanks,
--- Matthias
Hi all,
I am a bit disappointed about the MS Project leveling mechanism. It seems (and from the answer on another question I asked in this forum this was confirmed) that MS Project cannot automatically assign the remaining work time of a resource to another tasks (see thread "Balancing...
Thanks a lot for your quick answer, but I am afraid I did not describe precisely enough what I want to do:
I certainly do NOT want my resource to be overloaded. What I want is to let it operate with the exact capacity of 100% and make MS Project arrange the tasks appropriately in order to...
Hi everybody,
I am trying to do the following with MS Project 2000:
Task "Coaching" and "Work" are both handled by the Resource R1. As "Coaching" is a coaching task, R1 does not work with 100% on it. Instead, it is only assigned with 20% to this task. "Work" is a normal work task, R1 can work...
This site uses cookies to help personalise content, tailor your experience and to keep you logged in if you register.
By continuing to use this site, you are consenting to our use of cookies.