That works. Thank you very much for the extra effort. I really appreciate it. In the critical filter, I also had to un-check the "Show Related Summary Rows" box, plus I added an 'and' statement where Summary Equals No in the Critical filter.
Thanks PDQBach. I appreciate the quick response. I was afraid you would come back with the answer you gave me. I will see what I can do with a macro, or just change them manually.
I have stumbled on an interesting issue and hope someone can help. I am using MS Project 2003 Standard. In my schedule, I have milestone tasks that are on the critical path and the text is black. The diamond in the Gantt is red. I looked in the Text Styles menu for "Critical Milestone" so I can...
I'm sorry, I am not permitted to send my schedules out of the building. I will see if I can put a dummy schedule together that exhibits the problem, with the assumption that I can get it approved.
Regards
George
Thank You very much for your quick response PDQBach.
I tried your suggestions highlighting all the tasks and using the show/hide button. This works.
When I save, showing all the resources, they look OK as long as I save in the Task Usage view. If I change views, or filters, everything is...
I am having an issue with the Task Usage view. Hopefully someone can give me some guidance.
Normal operation of Task Usage:
When I select the Task Usage view, the "All Tasks" filter is used. All the tasks that are resource loaded display the resources and hours against each task in the entire...