Ok another problem--I have a huge schedule (some of it was partially cut and paste from another schedule)for some reason now when I assign a predasessor (sp?) it does not change the dates. It does not seem to be linking or shifting the rest of the days...what am I doing wrong? your help will be...
Is there a limit to letters one can put in a footer? when I print out my schedule, I have room to put more of a footer, however it will not allow me to add anything else to the footer-is there a way to change that?
Hello--Does anybody know if it is possible in Project 2003 to set up re-occuring events that don't necessarily have a task involved with it. For example, I would like to have meetings show up every other wed. of the month. Is this possible or do I just have to do it manually everytime? Thanks...