I have Project 2003. I was hoping I can have a column next to the task that shows difference between Baseline Start and Today -or- have the date difference print in the Gantt chart, next to the missed task.
Thanks in advance.
Thank you for replying!
I mean number of days between Baseline Start and Today. I'm in the very elementary stages of grasping Project, so bear with me.
Do you also know how to customize a printed report to only show a specific date range? My project is at least 5 years long, and the only way...
Can someone tell me how I can show amount of time past task start date on a report? I tried to use Slipping Tasks, but I can't seem to show number of days overdue.
Thanks!
I am a new user to Project, so bear with me. I need to create a way of tracking meetings with clients. I have over 300 clients. Would I set up each client as a Task? Each client has to meet at least once a year - so there is no project end date. I tried seting up a recurring task, but I could...
This site uses cookies to help personalise content, tailor your experience and to keep you logged in if you register.
By continuing to use this site, you are consenting to our use of cookies.