  1. piedpiper11

    Resource Usage Scrolling bug?

    Is this happening for anyone else? I am running MS Project Pro 2013 on a Win7 machine with 6 GB Ram and no issues. I'm managing a large project and the Resource Usage view is very clunky. In particular, when I have a resource that has a large number of assignments - that extend down past the...
  2. piedpiper11

    Why doesn't TimePhaseData read correctly?

    Can anyone explain to me why there are values reported for ActualWork when there shouldn't be in the following situation? I'm working with a dummy MPP that I created and I've assigned Work hours to the first seven tasks (through WBS 1.1.7). When you switch to the Task Usage view, you can see...
  3. piedpiper11

    Project 2013 Reporting: charts can show more than tables?

    I'm using Project 2013 Professional and the new & improved Reporting module. How come I can produce a nice chart of a particular resource's total hours to be Worked by Month, but I can't output the same data as a table to show exact monthly tallies? In other words, when I create a chart, and...
  4. piedpiper11

    Delinking accidentally referenced project files

    Hi There, I am working with a large single project in MS Project 2013 Pro. As I develop the project and major changes in project strategy occur, resulting in me needing to extensively edit the tasks, I have simply taken the latest MPP file, saved it with a new name, and started making task...
  5. piedpiper11

    Assignment Information Notes

    I just discovered that each assignment for a resource has an Assignment Information box (double click on any resource's task in Resource Usage view). And the box has a Notes tab, which is apparently unique to each resource in each task. I am in the process of developing specific Scope of Work...
  6. piedpiper11

    Spreading out Costs with the Task

    I'm using MS Project Pro 2013 and am fine tuning the cash flow of a project, where I'm having trouble getting the costs to span the project duration. In particular, I have a task, let's call it "Balance of System", which has multiple resources assigned. The largest one (90% of the total for...
  7. piedpiper11

    Filtering certain cost data from Reports

    I'm using MS Project Pro 2013 and having trouble getting certain tasks to disappear from the cost model. In a 500-task project, I have about 15 tasks sprinkled around that have negative costs (they are Materials-type resources, which I think is the only way I can get a negative number in the...
  8. piedpiper11

    Custom Field Formulas not responding correctly

    Hi all, I'm having trouble getting custom field formulas to work consistently. Of the four I've created, only one works right, and I can't see any difference in what I've done for the other three. Here's the situation: I am running a project (MS Project Pro 2013 on a Win7 system) that has to...
  9. piedpiper11

    Best accounting software to integrate with Project?

    Hey all, I am setting up a construction oriented project (about a $1.3 million total budget) and want to use MS Project (2013) to manage the project details. I also need to closely manage the accounting side so that my company can pay invoices, employees, subcontractors and the like, all...
  10. piedpiper11

    Auto-scheduling a recurring task to depend on another task

    Hi, I suspect this may not be possible from the reading I've done, but I thought I'd ask if anyone has any ideas. I have a construction project and the construction period starts at some point about 6 months from now, after a series of lead-up tasks are complete. During that construction...
  11. piedpiper11

    Why do Project Costs start 1-month early?

    I'm puzzled by seeing all my project costs start to show up one month early. This is for a major $1.5 million 2-year grant where the official grant contract start date is 7/1/13. However, I've started the plan in MS Project on 4/1/13 so I can track some pre-contract tasks. I've created a...