This is a little complicated. Let’s say I have 5 or so separate installation activities that each require the same WAP approval. Each of the these 5 activities have completion dates that move around a lot. I’d like the WAP done 10 days before the earliest of these 5 activities. How do I tie...
This site uses cookies to help personalise content, tailor your experience and to keep you logged in if you register.
By continuing to use this site, you are consenting to our use of cookies.