Hi Group,
Is there a way to enlarge views, such as the WBS area & Gantt or split screens?
MS Project does not appear to have these features like Excel & it's quite annoying, especially when attempting to put a large program together.
Thanks
Design Engineer Project Manager (DEPM)
Hi,
Is there a quick way to link desired predecessors, instead of manually typing in a series of them using MS Project 2010?
Thanks
Design Engineer Project Manager (DEPM)
Hi,
How can I have 0 (zero) as my first WBS ID? I did on past projects, but I don't recall how I did it before, since I've been away from MS Project for a while.
Now, using MS Project 2010.
Thanks
DEPM
Design Engineer Project Manager (DEPM)
Hi Group,
I’m trying to plan a project that has the following known & prospective parameters:
We want a project start date to be 08/20/12 & the target date to be 12/21/12. We are hoping to complete the whole project by the end of the year.
There are approximately 225 – 500 deliverables, which...
Hi Group,
Why does Gantt Chart View vs. Tracking Gantt views have radically different views? Also, why does one need individual headers & footers between to the 2 different style views?
I'm desperately trying to show the planned vs. actual project plan, but every time I adjust a date, it...