Dear all
The following is the definition in Program help of effort driven:
When a task is effort driven, Microsoft Office Project keeps the total task work at its current value, regardless of how many resources are assigned to the task.
When new resources are assigned, remaining work is...
Task types in MS Project 2007 does not act as in program help.
Case one:
For a fixed units task of 4 days duration and 8 hours/day using only one work resource R1 at 50% units to perform work of 16 hours, if I add a work resource R2 to this task at 50% units, program recalculates work to 32...
This site uses cookies to help personalise content, tailor your experience and to keep you logged in if you register.
By continuing to use this site, you are consenting to our use of cookies.