Hi,
When we split window with Gantt chart on top and resource view below (or vice versa), clicking on the top window causes a filter/shortlist on the below window. Is there any way to stop this?
What I want to do is (for big mpp's), adjust task dependencies and priorities such that that...
Hi,
I have seen below behaviour:
- A task A got split as there were some actuals before the start date followed by a work done on a different task
-Later there was a changing in project priorities with other project tasks getting higher priorities
- To make sure that half worked task A gets...