I would like to know how to total up all the durations on the critical path so I can see how long the critical path was before and after updating and rescheduling. Is there a simple solution other than exporting durations and totalising them after filtering for CP...
Hi Everyone, Lets see if I can explain this properly, I am a planning engineer and I am currently looking after a Scheme where we have reduced the programme (removing hidden float) and we have agreed with the client that we will track our Reduced Target date against his Contractual completion...
Hi Guys I am new and hoping you can help. I have a scenario where we have been asked by the client to price for extra works so we are also obliged to enter them into the programme. Unfortunately they go beyond the end of the current critical path and the end date of the project. As they are...