In my MSP % complete situation from yesterday, 11-04, i had 63% complete.
When i change the actual date for 12-04, today´s situation.
-Project>Project Information> Status Date: 12-04-2011
The %complete automatically turns 66%...
And after it, if i turn,
-Tools>Tracking>Update...
Hi everyone!
I would like to ask 2 things.
-First of all, what´s the main difference between %complete and %work complete?
-Second of all, in my Update Project, when I insert the column "%complete" the tasks wich didn´t start yet, comparing with the date i put in the.... Project>Project...