I have an MSP file that simply won't open ... no error message, MSP doesn't hang but the file remains closed.
A little background: we had problems with the file losing custom field lists so restored them from another similar plan. Then when I tried to close the plan it asked if I wanted to save...
Hi folks ...
Until recently I have been able to add a resource from a Resource Pool to a task and set the Units to 0% initially - this had the effect of leaving work assigned to existing resources unchanged. BUT in the last week or two MSP has started to recalculate the Work assigned to each of...
Hi Folks
I've had a little problem when using "Update Project" to reschedule a task I believed to be 100% complete.
A task had 10 hours spread over 4 days using a rate of $25/hr and MSP has planned:
Monday2.8hr$70
Tuesday2.8hr$70
Wednesday2.8hr$70
Thursday1.6hr$39.99
This totals 10hrs but...
HI folks
I previously asked about a problem we were having with custom fields being corrupted ... see: thread913-1705839
We are still getting this (or a very similar) problem and it's becoming a real pain.
In brief:
I run an macro to extract data including custom fields from all the plans in...
Hi Folks
This is really an irritating little problem. I have a skeleton project plan that is kept for creation of new standard plans. The problem I have with it is that although the project start date is set to March 2014, whenever I open the plan the Gantt chart is positioned at January 2012...
Hi folks
I am having a problem whereby the contents of some custom fields on two of our projects are being wiped, seemingly at random.
We are in the midst of moving from MSP 2007 on Windows XP to MSP 2010 on Windows 7 and during that process one of our PMs was accidentally upgraded to MSP 2010...
We appear to have a problem with calendars.
Please bear with me while I try to explain it because I'm not really sure I understand the problem....
We are running MSP 2007 and recently amended the bank holidays on the calendars held in the resource pool, now it appears that every time a plan is...
Hi guys,
we have recently converted from MSP 2003 to 2007 (some users were later moving than others, but the problem is continuing even though everyone is now on 2007).
Since the conversion we have noticed that on occasion MSP will decide to reallocate Actual Work that has previously been...