Can I add task name to the milestone bar to the left as the date is automatically placed to the right.
I have set up a column "Text 1" and copied the task names into it and have set the bar text up to display Text 1 to the right. Now I have made a second column "Text 2" but I can not get it to...
On a 2 shift project (2 x 12 hr shifts per day) what are the numbers of resources do I need to input as the "max units"
I have the following numbers per shift:
7 fitters
17 pressure welders
6 welders
10 riggers
10 labourers
Are these the correct "max units" I use or do I need to double up for...
I am trying to change the working hours on a project, I have sarted with a 24 hr calender as this project we will be working around the clock for 4 weeks.
I would like to step up the working day showing the meal breaks but I can only set up 5 periods.
Week 1 (single shift)
Start time 7:00am
1st...
Hi
Iam planning a boiler shutdown working 2 x 12 hr shifts for 14 days, can I change the format of the Start & Finish columns from Fri 19/06/09 to 8:00pm 19/06?
Thanks.
This site uses cookies to help personalise content, tailor your experience and to keep you logged in if you register.
By continuing to use this site, you are consenting to our use of cookies.