  1. SloopJohnB1

    Adding text to the milestone bar

    Can I add task name to the milestone bar to the left as the date is automatically placed to the right. I have set up a column "Text 1" and copied the task names into it and have set the bar text up to display Text 1 to the right. Now I have made a second column "Text 2" but I can not get it to...
  2. SloopJohnB1

    24 hr- (2 shift) Resource Sheet

    On a 2 shift project (2 x 12 hr shifts per day) what are the numbers of resources do I need to input as the "max units" I have the following numbers per shift: 7 fitters 17 pressure welders 6 welders 10 riggers 10 labourers Are these the correct "max units" I use or do I need to double up for...
  3. SloopJohnB1

    Changing working times

    I am trying to change the working hours on a project, I have sarted with a 24 hr calender as this project we will be working around the clock for 4 weeks. I would like to step up the working day showing the meal breaks but I can only set up 5 periods. Week 1 (single shift) Start time 7:00am 1st...
  4. SloopJohnB1

    Start & Finish

    Hi Iam planning a boiler shutdown working 2 x 12 hr shifts for 14 days, can I change the format of the Start & Finish columns from Fri 19/06/09 to 8:00pm 19/06? Thanks.