I am a bit disappointed about the MS Project leveling mechanism. It seems (and from the answer on another question I asked in this forum this was confirmed) that MS Project cannot automatically assign the remaining work time of a resource to another tasks (see thread "Balancing...
Hi everybody,
I am trying to do the following with MS Project 2000:
Task "Coaching" and "Work" are both handled by the Resource R1. As "Coaching" is a coaching task, R1 does not work with 100% on it. Instead, it is only assigned with 20% to this task. "Work" is a normal work task, R1 can work...