I am currently using version 9. HEre is the formula I am using:-
If wdaysClass1wdNumWorkDays (datevalue ({MPD_Manuals.ManualRequiredDate}), datevalue ({MPD_Manuals.DateCompleted}), "-23456-") = 0 then
Formula = 0
Else
Formula = wdaysClass1wdNumWorkDays (datevalue...
Hi everyone,
I can calculate the number of business days between two dates. If the release date is after the requried date eg late I get the correct number of working days, but In this instance the release date is before the required date eg released early(eg the required date of 1/1/04 and...
I want to add a leadtime eg 10 working days to an order date. I can add 10 calendar days using the DateAdd function
DateAdd("d", 10, #Sept 28, 1999#)but need to know how to add 10 weekdays.