    MS Project Work in summary task more than sum of subtasks

    Brilliant! Thanks Julie, that was the problem.
  2. brusselsshrek

    MS Project Work in summary task more than sum of subtasks

    I have a strange case in MS Project (2003) where a summary task takes more days Work than then sum of the Work of the subtasks. It seems to be using the Duration rather that the Work. Why? What can I do to force it to use the sum? I have created a very simple test project with this example...
  3. brusselsshrek

    MS Project Work in summary task more than sum of subtasks

    I have a strange case in MS Project (2003) where a summary task takes more days Work than then sum of the Work of the subtasks. It seems to be using the Duration rather that the Work. Why? What can I do to force it to use the sum? I have created a very simple test project with this example...