    Relative vs. absolute time/date in MS Project

    Greg, Assume that your task that starts on August 1 is Task 5. Also assume that the successor task is task 6. Assume that the start of task 6 is 5 days (work days) after the start of task 5. Also assume that you are using 'days' as the period for calculations In the task 6 predecessor field in...