I have an issue with importing data from excel into MS Project.
The issue I have is that I have tasks with fiexd work of f.i. 8 hours and a duration of 8 days. When I import this data, I get 8 days duration (this is OK!) but I get 64 hours of work (instead of 8 hours fixed work).
How can I...