I didnt get anything from your last reply. It doesn't make sense of what I need.
So I'll try and say this again:
I need an "Assign Resources" Dialog box to work (viewing Resource Names) for the duration of an entire task.
I understand what you mean. However, there should be some flex in MS-Project to do that.
So far, I came up with a Custom Filter such as this below:
Available From - Is less than or equal to - Start
Available To - Is greater than or equal to - Finish
You know what I need right?
I basically...
Hi PBQ,
Here's what I've got so far:
Task Name Days Start Resource Names
Analysis 1 day 4 jan jack
Design 1 day 4 jan matt
Building 4 days 24 jan jack
I want the Resources Names as listed above...
Hi PBQ,
Thanks very much for your email!
I did add the Tasks and Resources.
Now in the "Resources Names" column, I'm playing with the "Assign Resources" Dialog Box and would like to see which Resources are available for that task.
What approach must I take?
Hi Guys,
I want to design an "Assign Resources" dialog box
effectively that could pick resources available for a
task. My guess is you might need to use a custom
filter or a formula?
Scott