Thanks for the suggestion. I added the % Work Complete column to the project view, but it acts exactly the same way as the % Complete column does (ie. adjusts % work complete when changing the Begin or Finish dates for the task). Any other suggestions? Thx
Using Project 2003.
I am tracking several tasks in a project file and my manager needs to know an approximate % complete on a regular basis. Also on a regular basis we update the projected Finish date depending on resourcing, vacation schedules etc.
The issue I have is that when I change the...
Is there a way to set the Gantt Chart timescale to display a specific date range? We have a project file that rolls over from year to year and I would like to be able to have the Gantt time scale display only the current year (ie. Jan 1 - Dec 31 of the current year). Currently it starts...