hmm. this may be a 2003 srv sp1 vs 2003 clnt non-sp1 issue. or maybe just my client. the problem does not appear to be appearing on another box, so maybe this is not actually an issue?
i think i may have found a solution. Using resource allocation view and adjusting "assignment delay" along with duration (with fixed work task types) allows me to resolve my resource allocation issues. then i can still baseline. does this sound right?
here is a description of this problem i found on google groups which matches my situation... has anyone found a solution to this? In short, if i manually enter leveling delay or let project do leveling, and then i baseline, the baseline copies the right start date, but then changes the current...