I'm creating a report view in MS Project 2013 Standard, which is intended to show tasks due in the next two weeks.
I got the formula from here:
http://www.cambermast.com/agile-ideas-create-kanban-board-microsoft-project/
(([Start]>DateAdd(“d”,-14,now()) Or [Finish]>DateAdd(“d”,-14,now())) And...