Thanks JulieInMaine,
you are correct. I just inherited this plan and it has manual scheduling which I am not used to. I have left the task as manually scheduled and set the sub-task to automatically scheduled and it works fine.
It seems to be a bug though that manually scheduling recognises...
Hi,
in Project 2010, the task is for 45 days, there is one resource assigned at 100%. The Resource has 10 days holiday at the start of the task.
Project is calculating 36 days as it shows the resource working on the first day of the task even though the resource has a holiday on that day...