I am trying to export the Gannt chart to an Excel spreadsheet then import it into another application. By doing this regularly, I can synchronise the start / end dates of each task in the other financial application with MS project as it changes.
I am trying to preservee the parent child...
How do I find the Unique ID of the summary task header.
For Example:
Task 1 UID 1
Task 1_1 UID 2
Task 1_2 UID 3
Task2 UID 4
Task 2_1 UID 5
Task 2_2 UID 6
So if I am on Task 2_2 for example, the unique ID of its summary record would be 4.
I can find predecessor and...