Thank you, Julie. I greatly appreciate your help. You are correct, I am trying to say that any one of the members on the Brown team can perform the task. If I set the Brown Team units to 100% rather than 900%, how do I say that resource has 9 people on it? How is the Brown Team (9 people) at...
Thanks for both of your replies, Lillabeth and JulieinMaine. What I'm trying to account for is tasks that aren't owned by one person, but a team.
Each team is made up of 9 people, but only one will do the task. I just don't know which one. I also know that whoever does the task will take...
Lilliabeth,
So that I clearly understand, in the sample I provided, I should create a brand new task, with a brand new user and assign that task Fixed Work, Resource Unit = 100%. Then Save.
Then, do I need to go and update every resource in the gantt chart to have the calculation pick up? Or...
My project contains individual resources and teams set up as resources. Individuals have 80% max unit and teams have 800% max unit allocation.
Here's what I am having a problem with. I have a team (Blue 800%) that has (20+)tasks. Each task has a 1 day duration. Project is showing me that...