Thank you all. @Julie: I read your message too late. In the meanwhile I replaced the assignments saying "yes" to all questions "Resource has some actual work, sure to delete it?". I had not clear if "delete it" means "remove the resource from the activity transferring the actual work to the new...
Thank you Skip,
but - since I'm not able to even substitute IDs manually for the past activities - I would write a subsitution routine with same results as the manual operation :(
The problem is to tell Project to re-assign already performed activities.
Hi all,
I need some help: I consolidated three MS Project 2000 files. In the .mpp file, I observed that the same human resource appears under several out-of-standard typing (i.e. "John Smith", "J. Smith" and "Smith"). I created a new, correctly named resource (Smith John) and substitute the...