Thank you, I understand all your instruction (create tasks, display actual cost row...)but I just can't do this step:
"On the Actual Cost row for the resource (or the task), enter the costs the way you expect them to occur (front/back; irregular)" (I said that I could enter the number in the...
Thank again, PDQBach
I think I do make something wrong with my MS Project. I displayed Actual cost already on the righthandgrid, but I can not enter anything in these cells (as they were blocked), on the contrary, I can edit easily in the work cells. You all say that we can modify the...
Re-Hello BDQBach,
In fact, I try what you've told me but when I right-click on the actual cost, I can't edit it (the detail styles appears). To make you clear,my question is:
I have all tasks defined with duration, cost( initial budget)and the way of distributing cost along the duration(ex...
Thank you very much,(a good gift for my DOB :-)
I will try your way and keep you informed. By the way, could you please show me the way you track cost with Excel? I've never done it before and I really want to learn. Thanks in advance.
Hello,
I would like to know how we can change the methode of accrue cost in MS Project because there are just 3: prorotated, start or end, but I'd like to distribute 50% cost at start and 50% at the end of the task, or not prorotated but 30%,40%,30% for other task.
I see some suggesions that we...