1. I am using MSProject 2000.
2. By bar chart I was referring to the bar-graph portion of the Gantt Chart. It is my gantt table and gantt bar chart which are showing two different starting weeks. The table shows task starting W51/5 and the bar chart shows the task in Week 77.
Thanks for...
I am trying to show my task start and finish dates in weeks and I want it to calculate the weeks from the start of the project. Right now all I can get it to do is calculate from week 1 to week 52 of each year (example W51/5). The bar chart shows months and weeks from the start of the project...