Thanks for the help, but let me explain in a little more detail.
The file I createed is not saved as a template, it is a regular MS Project file. It has all the information that is common to 99% of all the projects I will use it for. It has the tasks, their durations, and their predecessors...
I created a project file with task start dates, durations, and predessors. None of the durations are estimates. I tried to use this file as a "template" for a new project that had a start date a few days later than the original. I had hoped that Project would re-schedule the project based on...