  1. beattirb

    Resource availability by task??

    exactly what I was looking for! thanks again PDQbach!
  2. beattirb

    Resource availability by task??

    Here's my situation: I have a task of a particular project that runs for a couple months. I have one resource assigned to this task. At this point the task is about 3wks from completion. The probelm is that the resource assigned to this task has to be used elsewhere, so I need to assign another...
  3. beattirb

    assigning equipment to tasks

    Interesting idea...I'm gonna do some work on that one. I'll let you know how it turns out. Thanks!
  4. beattirb

    assigning equipment to tasks

    Well I feel better knowing that I'm not just totally missing something! I figured this was the case, so I'll be sure to let you know if I find a better way. Thanks very much for you help, you certainly know what you're doing. thanks again!
  5. beattirb

    assigning equipment to tasks

    Seems you've explained this relationship many times before! I'd like to think I have a pretty good understanding of the work/units/duration relationship as I use it many times a day. I think maybe I'm just not explaining my point correctly, which I think is a very simple point. I'll try again...
  6. beattirb

    assigning equipment to tasks

    yes that is my understanding of how material works, which is fine. I guess I just have to get used to the fact that project treats equipment the same as an employee becuase equipment does work. I wish that I could just assign "welder 1" to a task without it contributing actual work, while at...
  7. beattirb

    assigning equipment to tasks

    The problem with switching a resource to a material is that it won't show overallocation probems. Unless I'm doing something wrong, I believe you can assign a material to mutltiple tasks occuring at the same time and the program won't see it as a problem. I guess if I want to assign equipment...
  8. beattirb

    assigning equipment to tasks

    Is there away to assign equipment to a task as a resource, without it changing the duration or work hours? For example if a resource "bob" is working on a task, and he needs "welder 1" for the whole task. I've tried doing it a couple ways, and it always messes up my hours and duration. Prjoect...
  9. beattirb

    Problem with holidays in calanders

    I've actually answered my own question with some more messin around. In the resource list, in the base calendar colum there was some calendar listed that doesn't exist and it was screwing everything up.
  10. beattirb

    Problem with holidays in calanders

    I'm having a problem setting vacation/holidays on my project. When I select a resource from my resource pool, and then click the "change working time button" I select the calendar that I want to use. (in this case standard) However, once i click ok to save the change in calendar, it resets...
  11. beattirb

    Using MS Project Calendars for Holidays

    Um, yeah that would probably be much more useful huh? I just joined this thing so I didn't know that existed. Thanks!
  12. beattirb

    Using MS Project Calendars for Holidays

    I'm having a problem setting vacation/holidays on my project. When I select a resource from my resource pool, and then click the "change working time button" I select the calendar that I want to use. (in this case standard) However, once i click ok to save the change in calendar, it resets...