Example#1:
Given the resource calendars:
resource01 24 hours a day [machine]
resource02 08:00-12:00; 13:00-17:00 [man01]
resource03 17:00-20:30; 21:00-01:20 [man02]
If 1 task has these 3 resources, the task can only evolute if theres at least one man working with the machine (two shift...
I've got one task which has two resources, for example:
1 - one man
2 - one machine
Both resources at first were assign with Stand Calendar
8:00-12:00 13:00-17:00
After that I've changed their calendar (resource calendar) to be set with:
The man works 24hrs a day (!! just an experience)
The...