Sorry, I was out of the office for a few days, but I finally figured out what the problem was...apparently in Project 2010 "Start" is not really (no longer?) a date field, "Scheduled Start" is the field 2010 uses to start a task, so once I changed my map to point to "Scheduled Start", the...
Julie,
I've got Project 2010 (14.0.6023.1000) SP1 MSO (14.0.6106.5005)
And I created a simple Excel file as you suggested, but for some reason, can't get the Import Wizard to open up when I point to the Excel file like I do with my Access database. I'm doing to same thing, opening up my...
I assume you're talking about the "New tasks created:" option is set to Auto Scheduled, under the Project Options/Schedule section? Which it is...or is there a "new task mode" somehwere else? Thanks!
Not sure this is the right forum, but I could really use some help mapping fields from an Access database into Project. I recently had to upgrade from Project 2007 to 2010 and ever since then have had problems using an existing map. The initial problem I ran into was getting “OUT OF...
This site uses cookies to help personalise content, tailor your experience and to keep you logged in if you register.
By continuing to use this site, you are consenting to our use of cookies.