I would like to know how to get dependent tasks to start on the date “after” its predecessor finishes. Currently all my dependent tasks start on the finish date of their predecessor task. For example: Task 1 finishes on Aug 27 and Task 2 starts on Aug 27. Here are some details about how I set...