Hi all,
I hope someone will be able to clarify this for me:
I am using Project to track work and schedule.
Let's say I have a task (type = Fixed work) that has 8 hours of work and 1 resource allocated at 100% units and the calendar working time is 8hours per day. Let's say the resource has...