Thanks that has sorted it, I basically created a large exception in the calendar until the supplier start date, it's interesting to know that if you stagger available work by date it has a similar affect as applying a back loaded contour
Hi,
I've been informed by a contractor of a particular date that they are able to commence work for us. They will be doing work throughout the project but will be unable to begin until later next month. I want the tasks in MS project to reflect that but I do not want to constrain the individual...