I know this is alittle late May to July but if you go into the Gantt View and right-click on the bar and select split, you can split your task as many times as you like across the full duration of the project.
Hi Scott,
Possibly the solution you are looking for is as follows:
1) Be in the Gantt Chart with the diagram visible
2) Right-click on the bar that shows your duration. It will bring up a menu and select split. Follow its instructions from there.
Regards,