Hi,
in MS Project 2000, I've added a periodic task,
e.g.
- name: DoHouseWashing
- duration: 1 day
- every week at Monday
- starts March, 18th
- until end of 2002
In the Gantt Chart, I can see the duration column
displayed, and it shows the total duration until
completition (286 days)...