Hi, thanx for reading this,
I have made several maintenance projects which consist only of recurring tasks. The program runs in a sequence of 5 years. The tasks fit within these 5 years and may start earlier or later. The resources added to the tasks have an average over-capacity of 200%...
Leveling problems with recurring tasks in MS-project 2000.
I have made several projects with only recurring tasks (maintenance planning). My resources show an overallocation in different periods. I am certain the plan does not exceed the project duration and that it is possible to delay tasks...