using 2007. The Project Start and Project Finish dates are showing as the same date in the Project Summary. However, in Project Information the Finish date is correct.
Anybody have a clue?
GEM
here is one way to do it.
select Date9 (give it name also)
and enter formula [Status Date]
select Date10 (name it)
and enter Formula [Status Date]+40
create a filter and title it "60 Day" (copy the Date Range and modify)
first line Start >= "Start Date:"?
2d line...
I received a 2007 project that is 28mb. I saved it with another name to preserve the original - example ABC Project rev b.mpp saved as ABC Project rev b - gem.mpp
I can work in the new "gem" file and make changes etc. However, once I save and close it, I cannot open it again. I get "an...