Thank you for your reponses.
This situation is not occuring by changeing the percent complete - it is happending by changing the task date to several days before the initial date.
FYI - I uninstalled project 2003 and reinstalled it and attempted to clear the registry entries to ensure a...
I've been using MS Project 2003 for several months. Pretty basic usage - linked tasks, general ghantt chart.
All of a sudden, as of just now, when I change the date for a task, none of the dates in the linked tasks change.
Is there a setting or something else that I have inadvertantly...