Hi folks,
as a beginner in MS Project, I am hoping I can get some information here.
I have 2 tasks in my Project PLan
Task 1: 5 days: Start June 01-June 05
Task 2: 10 days: Start June 06-16
Task 2 id dependent on 1.
However, I finish task 1 in 2 days and I want the system to reschedule Task...