Hi,
When we split window with Gantt chart on top and resource view below (or vice versa), clicking on the top window causes a filter/shortlist on the below window. Is there any way to stop this?
What I want to do is (for big mpp's), adjust task dependencies and priorities such that that...
Hi Julie,
Well, yes if turning splits off is possible temporarily to solve this issue (and then I should be able to keep splits on again without disturbing it).
I need splits on because:
- we have some recurring support tasks which should split reguler work
- To ensure optimal resource...
Do you mean the setting for Critical in Options-> Calculation?. The setting identifies tasks with 0 slack as critical. I dont think the pending part of the split task A was critical - I was just relying on priority to have it done earlier.
Do you reckon setting number of days of slack...
Hi,
I have seen below behaviour:
- A task A got split as there were some actuals before the start date followed by a work done on a different task
-Later there was a changing in project priorities with other project tasks getting higher priorities
- To make sure that half worked task A gets...