Got it. I removed the assignment at the summary task level and that seems to have fixed my problem. I also removed the manually-assigned Web_80 calendars and it is still working fine since both the resource and project calendars are using the same default.
I still have a question about the...
Hi. I am very much a MS Project noob and I have two questions about this simple project (attached) which are really bugging me:
1. why does it say my resource is over allocated (when it isn't - look at task ID 23, working 1 hour on a workday)
2. I put together steps of an outlined project...