Hi all,
I am working around to find a solution to define activity as a constraint to other activity.
For example, there is set of 15 activities (A1, A2, ...,etc.).
Activities A5 and A10 are such that, during their execution period other all activities must not executed or else to be paused.
I...
In MS project, by using gantt chart wizard, we can find critical path of the schedule. but how to find next critical path, if first critical path become normal activity, then how to find which activity path will be the next critical activities ?