  1. Soikkendaal

    How to print a basic report to a file to be copied and pasted to word / excel

    hello again is there a possibility to print - let's say a basic report of project costs - to file? so that I could then copy and paste the values to excel to process them further? soili
  2. Soikkendaal

    Creating a new baseline after changes in project scope

    hi here's my situation: have made a project plan with agreed tasks and duration and set a baseline. the project has been going on for several weeks and actual work reported. now changes are needed (and approved by the steering): two extra resources are needed in the project because of an extra...
  3. Soikkendaal

    Earned Value Over Time Report - how to create?

    in my projects i need to use the physical % complete, because usually the if half of the work is used it does not necessarily mean that half of the task is ready...have to make the earned value graphichs manualluy. thank you for your interest in my problems soili
  4. Soikkendaal

    Earned Value Over Time Report - how to create?

    hi, now i know what is the problem. when i use physical % complete as the earned value method (as i usually) then the visual report does not work. BUT when the method % complete is used, also the report is working.
  5. Soikkendaal

    Earned Value Over Time Report - how to create?

    i have tasks, amount of work and then resources named for the task. each resource has a cost per day value. when i'm fig. on the tracking gantt view i get all correct values for bsws, acwp and bcwp, as well as cpi and spi. but...visual report does not give the proper result. what do you mean by...
  6. Soikkendaal

    Earned Value Over Time Report - how to create?

    hi i have them all, because i get the bcwp, cpi and spi figures based on a date when i'm on the gantt view?!? soili
  7. Soikkendaal

    Earned Value Over Time Report - how to create?

    hi, i have a problem to crate a proper earned value report. how to include the values...is just get two dots on the report or then the planned value and actual value is ok, byt earned value just a straight line?!?
  8. Soikkendaal

    How to update/recalculate the plan after updating actual work with wrong figures

    yes, you're rught: i made a mistake, had two cpi's instead of cpi and spi. is it so that after setting the baseline to a project i should only work wtht the tracking gantt view? soili
  9. Soikkendaal

    How to update/recalculate the plan after updating actual work with wrong figures

    ok, so the adjustement must be done manually...thank you for this tip. by the way: i'm using the earned value method. surely you know: why is the spi or cpi value different when i'm on the tracking gantt view of when i'm on the 'normal' gantt view?!?
  10. Soikkendaal

    How to update/recalculate the plan after updating actual work with wrong figures

    hi julieinmain no, the task is not complete... soili
  11. Soikkendaal

    How to update/recalculate the plan after updating actual work with wrong figures

    hi,I need your help! my situation: I updated my project with actual work figures. the baseline work of one task was 15 hours. by mistake i added 15 days. my trackin gantt of course reacted this and channged the duration etc. then i updated the actual work - now with correct figures: 15 hours -...